Phase 1 Schedule: 15 weeks complete out of 22 weeks

Construction Progress

Architectural 25%
Mechanical 35%
Electrical 38%
Plumbing 40%
Fire Protection 10%

Overall Progress

Overall Project 33%
*Percentage based on Payment Requisition #4, 11/1/21 – 11/30/21